Application setup
Setting Up Arc Welding Parameters on a Robot
For process engineers and welders configuring weld schedules on a robotic arc welding cell, from power source communication to weave and crater fill settings.
- Step 1.
Confirm power source communication
Verify the robot controller and welding power source are communicating over their digital interface and that basic status signals report correctly.
- Step 2.
Enter the base weld schedule
Set voltage, wire feed speed or current, and travel speed according to the welding procedure specification for the joint and material.
- Step 3.
Configure arc start and end conditions
Set initial current and voltage for arc start, along with crater fill parameters for the end of the weld to prevent crater cracking.
- Step 4.
Set weave parameters if required
Configure weave pattern, width, and dwell time for joints that need it, based on the WPS.
- Step 5.
Configure gas pre-flow and post-flow
Set shielding gas timing before arc start and after arc end to ensure proper coverage.
- Step 6.
Teach the weld path
Put the robot in Teach Mode (T1) at reduced speed with the enabling device held before jogging the torch. Program the travel path with correct torch angle and work angle for each pass, referencing the WPS. Do not teach or edit points while the cell is in automatic or high-speed mode.
Caution: Never program robot motion under power outside Teach Mode T1 with reduced speed and the enabling device active. Keep all other personnel clear of the robot envelope while teaching.
- Step 7.
Weld test coupons
Run the program on test material and inspect the weld against the acceptance criteria in the WPS.
- Step 8.
Fine-tune and lock the schedule
Adjust parameters based on coupon results, then document and lock the finalized schedule for production use.
Common questions
- How long does Setting Up Arc Welding Parameters on a Robot take?
- Setting Up Arc Welding Parameters on a Robot is rated Intermediate and takes about 90 minutes across 8 steps.
- What tools do I need?
- You will need Teach pendant, Welding power source with robot interface, Test coupons and welding consumables.
- What should I do before starting?
- Power source connected to the robot controller via its digital interface. Welding procedure specification (WPS) for the joint.
- What is the first step?
- Confirm power source communication. Verify the robot controller and welding power source are communicating over their digital interface and that basic status signals report correctly.